Roundabouts in Oshkosh
For more information on the projects below click here.
- Jackson Street and Murdock Avenue - Completed June 25, 2010


Before and after photos of Jackson Street and Murdock Avenue
- US Highway 45 and Fernau Avenue - Scheduled Completion by August 2010

- Witzel Avenue near US 41 (2 roundabouts) - Scheduled Completion by September 2010

- 9th Avenue near US 41 (4 roundabouts) - Scheduled Completion by July 2011

- US Route 45 west of US 41 - Scheduled Completion by November 2011
- STH 21/Washburn Street/Brooks Lane and STH 21/Koeller Street (2 roundabouts) - Scheduled Completion by July 2012

- Oshkosh Avenue/Omro Road (STH 21) at US 41 ramps (2 roundabouts) - Scheduled Completion by November 2012